L 38/179
Register summary
- Holder
- Laverton Gold Pty Ltd
- Part of
- Genesis Minerals Limited (ASX:GMD) as at 2026-06-30
- Local government
- Shire of Laverton
- Application received
- 20 July 2010
- Commenced
- 5 July 2011
- Expiry
- 4 July 2032
- Term
- 21 Years
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A135963 | 2023 | Sammy Resources Pty Ltd | Yabby | 1.1% | Final Surrender Report for E38/3425 - Yabby Project for the period ending 27/03/2023 |
| A130822 | 2022 | Sammy Bakie | Yabby | 1.1% | E38/3425 Annual Report Yabby Project for the period ending 27/03/2022. |
| A126519 | 2021 | Rincon Resources Limited | Laverton | 2.6% | Laverton Project E38/2908 (C116/2020) Partial Surrender Report for the period ending 20 January 2021 |
| A122997 | 2020 | Rincon Resources Limited | Laverton | 2.6% | Annual Exploration Report E38/02908 Laverton for the period ending 22/01/2020 |
| A124221 | 2020 | Focus Minerals (Laverton) Pty Limited; Focus Minerals Ltd | Central Laverton | <1% | Central Laverton C119/2014 Annual Technical Report for the period ending 28/02/2020 |
65 more reports
| A119469 | 2019 | Holding Tenements Pty Ltd | Laverton | 2.6% | Annual Exploration Report Laverton Project E38/2908 for the period 23rd January 2018 to 22nd January 2019 |
| A120411 | 2019 | Focus Minerals (Laverton) Pty Limited; Focus Minerals Ltd | Central Laverton | <1% | Central Laverton C119/2014 Annual Technical Report for the period 1 March 2018 to 28 February 2019 |
| A116744 | 2018 | Holding Tenements Pty Ltd | Laverton | 2.6% | ANNUAL EXPLORATION REPORT LAVERTON PROJECT E38/2908 FOR THE PERIOD 23/01/2017 - 22/01/2018 |
| A116824 | 2018 | Focus Minerals (Laverton) Pty Limited; Focus Minerals Ltd | Central Laverton | <1% | Central Laverton C119/2014 Annual Technical Report For the Period 1 March 2017 to 28 February 2018 |
| A112332 | 2017 | Holding Tenements Pty Ltd | Laverton | 2.6% | ANNUAL EXPLORATION REPORT LAVERTON PROJECT E38/2908 FOR THE PERIOD 23/01/2016 - 22/01/2017 |
| A112029 | 2017 | Poseidon Nickel Limited | Laverton West | <1% | Laverton West E38/1930 Surrender Report for the period 13/04/2007 to 11/05/2016 |
| A113931 | 2017 | Focus Minerals (Laverton) Pty Limited | Central Laverton | <1% | Combined Annual Report C119/2014 Central Laverton Project for the period 1 March 2016 to 28 February 2017, E38 |
| A108204 | 2016 | Poseidon Nickel Limited | Laverton West | <1% | West Laverton (C85/2014) Annual Technical Report 01/01/2015 - 31/12/2015, E 38/01930, M 38/00372, M 38/00694, |
| A108862 | 2016 | Focus Minerals (Laverton) Pty Limited | Central Laverton | <1% | Combined Annual Report C119_2014 Central Laverton Project for the period 1 March 2015 to 28 February 2016 |
| A104754 | 2015 | Poseidon Nickel Limited | Laverton West | <1% | C85/2014 LavertonWest Project - Annual Report for the period 1 January 2014 to 31 December 2014, E38/1930, M38 |
| A105958 | 2015 | Focus Minerals Ltd | Central Laverton | <1% | Combined Annual Report Central Laverton Project - C119/2014 Western Australia For the Period 1 March 2014 to 2 |
| A102352 | 2014 | Poseidon Nickel Limited | Laverton West | <1% | Laverton West Project E38/1930 for the period 13 April 2013 to 12 April 2014 |
| A102282 | 2014 | Focus Minerals Ltd | Central Laverton | <1% | Central Laverton Project, C310/2011, Combined Annual Report, 01/03/2013 to 28/02/2014, E38/1349, E38/2203, M38 |
| A98404 | 2013 | Focus Minerals (Laverton) Pty Ltd | Central Laverton | <1% | Central Laverton Project, Annual Report for the period 01/03/2012 to 28/02/2013, E38/1349........E38/2321;M38/ |
| A96708 | 2013 | Classic Minerals Ltd | Sunshine | 3.1% | Sunshine Project Annual Report, E 38/2084 for the period 26 September 2011 to 25 September 2012 |
| A97205 | 2013 | Focus Minerals (Laverton) Pty Ltd; Panoramic Resources Ltd | West Laverton | <1% | West Laverton Project, Annual Report for the period 30/11/2011 to 29/11/2012, E38/1930; E39/1296; M38/46, 372, |
| A98016 | 2013 | Focus Minerals (Laverton) Pty Ltd | West Laverton | <1% | PARTIAL SURRENDER REPORT ON EXPLORATION FOR THE PERIOD 13 APRIL 2007 to 12 APRIL 2013 Tenement: E38/1930 [West |
| A92398 | 2012 | Classic Minerals Ltd | SUNSHINE | 3.1% | Sunshine Project Annual Report, E 38/2084 Report Period 26-9-2010 to 25-9-2011 |
| A92841 | 2012 | Crescent Gold Ltd; Magma Metals Ltd; Poseidon Nickel Ltd | West Laverton | <1% | West Laverton Project, Annual Report for the period 30/11/2010 to 29/11/2011, E38/1930; E39/1296; M38/46, 372, |
| A93988 | 2012 | Crescent Gold Ltd | Central Laverton | <1% | Combined Annual Report on Exploration for the period 01/03/2011 to 28/02/2012; Central Laverton Project; C310/ |
| A92691 | 2012 | Crescent Gold Ltd | Central Laverton | <1% | Interim Combined Annual Report on Exploration for the period 01/03/2010 to 28/02/2011; Central Laverton Projec |
| A89806 | 2011 | Crescent Gold Ltd | West Laverton | <1% | Combined Annual Report on Exploration for the period 01/01/2010 to 31/12/2010; West Laverton Project; C5/2011 |
| A90143 | 2011 | Crescent Gold Ltd | Central Laverton | <1% | Combined Annual Report on Exploration for the period 01/01/2010 to 31/12/2010; Central Laverton Project; C6/20 |
| A86798 | 2010 | Barrick (Australia Pacific) Ltd | Laverton | <1% | Project 8871 Laverton Joint Venture Annual Report period 1 January 2009 – 31 December 2009, Technical Report N |
| A88399 | 2010 | Classic Minerals Ltd | Sunshine | 3.1% | Sunshine Project Annual Report, E38/2084, 26/09/2009 to 25/09/2010 |
| A82038 | 2009 | Barrick Gold Of Australia Ltd | Laverton Exploration JV | <1% | LAVERTON EXPLORATION JOINT VENTURE ANNUAL, REPORT Period 1 January 2008 – 31 December 2008 TECHNICAL REPORT No |
| A78114 | 2008 | Barrick (Granny Smith) Pty Ltd | Laverton | <1% | PROJECT 8871, LAVERTON Project, (ALL TENEMENTS), ANNUAL REPORT, Period 1 January 2007 31 December 2007, TECH |
| A75073 | 2007 | Barrick Gold Of Australia Ltd | Laverton | <1% | Project 8871, Laverton Project, Annual Report, Period 1 January 2006 - 31 December 2006, Technical Report No.1 |
| A72705 | 2006 | Barrick Gold Of Australia Ltd | Laverton | <1% | Laverton Exploration JV, Annual Exploration Report for the Period 1 January 2005 to 31 December 2005, Combined |
| A69813 | 2005 | Metex Resources Ltd | Laverton | <1% | Annual report for the period 01/02/04 - 31/12/04 Laverton Exploration Project, C5/2002, E38/411, E38/556, E38/ |
| A70391 | 2005 | Crescent Gold Ltd | Enniskillen | <1% | Enniskillen Project, Combined Annual Report, C117/1997, Leases M38/236, M38/270, M38/342, M38/345, M38/394, P3 |
| A68420 | 2004 | Apollo Gold Mining Ltd | Enniskillen | <1% | Annual report for the period 01/01/2003-31/12/2003 Enniskillen Project (C117/1997), M38/0236, M38/0270, M38/03 |
| A68953 | 2004 | Metex Resources Ltd | Laverton | <1% | Laverton JV Project (C5/2002),Annual Report for the period 01/02/2003-31/12/2003 Laverton JV Project (C5/2002) |
| A66229 | 2003 | Sons Of Gwalia Ltd | Enniskillen Project | <1% | Enniskillen Project,Annual Report for the period 1 January 2001 - 31 December, 2002 C117/1997: M38/236, M38/27 |
| A66477 | 2003 | Metex Resources Ltd | Laverton | <1% | 2002 Annual Report for period 01/02/02 to 31/12/02 Laverton Exploration Joint Venture C5/2002: E38/389, 406, 4 |
| A65027 | 2002 | Metex Resources Ltd | Laverton | <1% | Combined Annual Technical Report, Laverton Project, Lancefield Tenement Group (DME Ref: C382/1995) Laverton, W |
| A62396 | 2001 | Sons Of Gwalia Ltd | Enniskillen | <1% | Enniskillen Project Annual Report For The Period 1 January 2000 - 31 December 2000. Tenements: M38/236 M38/270 |
| A62445 | 2001 | Metex Resources Nl | Laverton | <1% | Combined Annual Technical Report Period 1 February 2000 To 31 January 2001. Laverton Project Lancefield Teneme |
| A62582 | 2001 | Metex Resources Ltd | Sunshine | 5.1% | Annual Report for the period 2nd May 2000 to 1st May 2001, Sunshine Project, E38/851. |
| A60004 | 2000 | Metex Resources Nl | Sunshine | 5.1% | Annual Report for the period 02/05/1998 to 01/05/1999, Sunshine Project, Exploration Licence 38/851 |
| A60731 | 2000 | Metex Resources Nl | Laverton/Lancefield | <1% | Combined Annual Technical Report Period 01/02/1999 to 31/01/2000 Laverton Project, Lancefield Tenement Group E |
| A57921 | 1999 | Metex Resources Nl | Laverton | <1% | Laverton Project, Laverton Exploration J.V. Beasley Creek Oxide J.V. 01/02/1998 - 31/01/1999 E38/658, 822 |
| A59191 | 1999 | Sons Of Gwalia Ltd | Enniskillen | <1% | Enniskillen Project. Annual report for the period 01/01/98-31/12/98. M38/236,270,342,345,394. P38/0452,2322,26 |
| A54899 | 1998 | Metex Resources Nl | Laverton | <1% | Laverton Project - Lancefield Tenement Group E38/365, 822, 835, M38/37, 38, 39, 40, 45 etc. 01/02/97 - 31/12/9 |
| A55648 | 1998 | Metex Resources Nl | Sunshine | 5.1% | Annual Technical Report for the period 2nd May 1997 to 1st May 1998 W123-Sunshine Project, Exploration Licence |
| A52324 | 1997 | Metex Resources Nl | Sunshine | 5.1% | Sunshine Project , Annual Report for the period 02/05/1996 to 01/05/1997, E38/851. |
| A51243 | 1997 | Metex Resources Nl | Lancefield | <1% | Annual Technical Report Period 1 Febuary 1996 to 31 January 1997 Laverton Develpment Project Lancefield Teneme |
| A51454 | 1997 | Sons Of Gwalia Ltd | Enniskillen | <1% | Laverton Region Enniskillen Project Annual report for the period 1st January 1996 to 31st December 1996 Teneme |
| A51820 | 1997 | Sons Of Gwalia Ltd | Enniskillen | <1% | Enniskillen Annual report for the period 15/04/94 to 18/08/96 Tenements M38/342 M38/345 P38/2315 P38/2316 Repo |
| A55360 | 1997 | Sons Of Gwalia Ltd | Enniskillen | <1% | Enniskillen Project Annual report for the period 01/01/97 to 31/12/97 M38/236, M38/270, M38/342, M38/345, P38 |
| A48547 | 1996 | Metex Resources Nl | Lancefield | 1.1% | Annual Technical Report Period 1 Febuary 1995 to 31 January 1996 Laverton Development Project Lancefield Tenem |
| A43233 | 1995 | Western Mining Corporation Ltd | Windarra | <1% | Technical Report Windarra Leases for the period 01/07/93 to 31/12/94 (AML70/261, M38/38 to M38/43, M38/45 to M |
| A41815 | 1994 | Sons Of Gwalia Ltd | Mount Ajax | 4.4% | Annual report for the period 20/08/93-19/08/94, Mt Ajax Project,E38/519. |
| A43145 | 1994 | Western Mining Corporation Ltd | Windarra | <1% | Technical Report Windarra Leases for the period 01/07/92 to 30/06/93 Windarra Nickel Project (M38/38 to M38/43 |
| A38474 | 1993 | Ashton Mining Ltd | Gladiator | <1% | Gladiator Project, Annual Report for the period 1st January 1992 to 31st December 1992, GML38/2810, M38/66 & 2 |
| A35126 | 1992 | Western Mining Corporation Ltd | Mount Windarra | <1% | Mount Windarra Project, Annual Report for the period 01/07/1989 to 30/06/1991, SA261;M38/38-43, 45-49, 52-53, |
| A35680 | 1992 | Ashton Gold Wa Ltd | Gladiator | <1% | Gladiator Project, Annual Report for the period 1st January 1991 to 31st December 1991, GML38/2810; M38/66 & M |
| A34630 | 1991 | Ashton Gold Mines Pty Ltd | Gladiator South | <1% | Gladiator South Project, Annual Report for the period 1st January 1990 to 31st December 1990, M38/203. |
| A17957 | 1990 | Ashton Gold Mines Pty Ltd | Gladiator South | <1% | H439 Gladiator South Project Annual Technical Report for the period 01/01/89 to 31/12/89 M38/203 (replaced P38 |
| A31396 | 1989 | Western Mining Corporation Ltd | Windarra | <1% | Technical Report; Windarra Leases For The Period 1 July 1988 to 30 June 1989. (Annual Report M38/38 to 43, M38 |
| A6945 | 1973 | Kennecott Exp Aust Pty Ltd | Erlistoun | <1% | Aeromag- Raw Data |
| A3075 | 1971 | Scamander Mining Corp Nl | Garden Well | 5.4% | Garden Well Project, Non-statutory Report: Progress Report(s) on Investigations,for the period ending 31st Dec |
| A43079 | 1753 | Western Mining Corporation Ltd | Windarra | 19% | Technical report - West Gladiator Prospect for the period 22/12/92 to 31/12/94 (M38/358, M38/399, P38/1722, P3 |
| A85671 | 1753 | Classic Minerals Ltd | Sunshine | 3.1% | Sunshine Project Annual Report, E38/2084, 29/9/2008-25/9/2009 |
| A38751 | 1753 | Inco Australia Ltd | Eastern Goldfields regional mapping | <1% | Eastern Goldfields regional mapping |
Tenure detail Free account
- Current holders & shares
- Holder change history
- Expenditure history
- Conditions & endorsements
- Native title context
- Combined reporting
- Rent status
Tenement intelligence Premium
- Time to expiry
- 6 years · 4 July 2032
- At-risk & opportunity signals
- Expenditure compliance
- 5-year track record
- Spend trend & exploration intensity
- Expiry band
- Ownership age
- Dealings, mortgages & caveats
- Transfer history
What does the exploration record say about this ground?
NextMaps reads every WAMEX report over L 38/179 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps — every claim cited back to its source report. New accounts include a free prospectivity report. Prefer the raw due diligence? The Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Open on the map — full register record About AI reports About Tenure PacksDo you hold L 38/179? Listing is free. A facilitation fee applies only if the ground ends up with a buyer we introduce.
List this tenementTenure data sourced from the DMPE public registers and SLIP WA (© Government of Western Australia, CC BY 4.0), as at 2026-09-27. Compiled by NextMaps. Verify against primary sources before reliance.