| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A149832 | 2025 | Brightstar Resources Limited | Sandstone | <1% | Partial Surrender Report for E57/1108 Sandstone for the period ending 30/06/2025. |
| A137242 | 2023 | Sls Exploration Pty. Ltd. | Dandaraga | <1% | Final Surrender Report E57/1028 - Dandaraga Project for the period ending 13/07/2023 |
| A129532 | 2022 | Alto Metals Limited | Edale Shear Zone | 13% | Alto Metals Edale Co-funded Drilling Report, R22 |
| A133108 | 2022 | Alto Metals Limited | Sandstone | 13% | Sandstone Gold Project E57/1031 Partial Surrender report for the period ending 06/10/2022. |
| A133180 | 2022 | Alto Metals Limited | Sandstone | 18% | Sandstone Gold Project E57/1033 Partial Surrender report for the period ending 07/10/2022. |
77 more reports
| A128149 | 2021 | Sls Exploration Pty. Ltd. | Dandaraga | <1% | Dandaraga Project E57/1028 Annual Report for the period ending 14/07/2021 |
| A129048 | 2021 | Firehouse Wa Pty Ltd | E 57/1118 | <1% | Annual Report for Exploration License E 57/1118 for the period ending 13/10/2021 |
| A124638 | 2020 | Sls Exploration Pty. Ltd. | Dandaraga | <1% | Annual report E57/1028 Dandaraga project for the period 15 July 2019 to 14 July 2020 |
| A125025 | 2020 | Gateway Mining Limited | Gidgee | <1% | Annual Report – E57/1108 – Mt Dwyer, 1 July 2019 to 30 June 2020 |
| A125623 | 2020 | Firehouse Wa Pty Ltd | Sandstone | <1% | Annual Report for Sandstone E57/1118 for the period 14 October 2019 to 13 October 2020 |
| A120744 | 2019 | Sls Exploration Pty Ltd | Dandaraga | <1% | Annual Technical Report Dandaraga Project E57/1028 For the Period 15 July 2018 to 14 July 2019 |
| A121869 | 2019 | Alto Metals Limited | Sandstone Group 2 | 13% | Sandstone Project C24/2017 Combined Annual Report for the period 20 September 2018 to 19 September 2019 |
| A117626 | 2018 | Sls Exploration Pty Ltd | Dandaraga | <1% | Annual Report Dandaraga project, Sandstone SLS Exploration, 15 July 2017 - 14 July 2018 |
| A118569 | 2018 | Alto Metals Limited | Sandstone | 13% | Sandstone Project C24/2017 Combined Annual Report for the period 20 September 2017 to 19 September 2018, E57/0 |
| A115491 | 2017 | Alto Metals Limited | Sandstone 2 | 13% | Sandstone Project C24/2017 Combined Annual Report for the Period 20 September 2016 to 19 September 2017, E57/0 |
| A114488 | 2017 | Sls Exploration Pty Ltd | Dandaraga | <1% | Annual Technical Report E57/1028 Dandaraga Project for the period 15/07/2016 - 14/07/2017 |
| A108818 | 2016 | Black Oak Minerals Limited | Sandstone | <1% | SANDSTONE PROJECT C28/2005 Combined Annual Report for the period 1 January 2015 to 31 December 2015, E57/580, |
| A105480 | 2015 | Black Oak Minerals Limited | Sandstone | <1% | Combined Annual Report for the Sandstone Project C281/2005 for the period 1 January 2014 to 31 December 2014, |
| A101260 | 2014 | Southern Cross Goldfields Ltd | Sandstone | 42% | Sandstone Project E57/703-I Partial Surrender Report for the period 7/01/2008 to 06/01/2014 |
| A101991 | 2014 | Southern Cross Goldfields Ltd | Sandstone | 3.8% | Combined annual report for the Sandstone Project, East Murchison Mineral Field, for the period 1 January 2013 |
| A103800 | 2014 | Southern Cross Goldfields Ltd | Sandstone | 42% | SANDSTONE PROJECT E57/703-I East Murchison Mineral Field Final Surrender Report for the period 7/01/2008 to 21 |
| A98388 | 2013 | Southern Cross Goldfields Ltd | Sandstone | 3.3% | Final Surrender Report for the Sandstone Project, E57/584, for the period 5 October 2005 to 15 March 2013 |
| A98390 | 2013 | Southern Cross Goldfields Ltd | Sandstone | <1% | Final Surrender Report for the Sandstone Project, E57/877, for the period 20 October 2011 to 15 March 2013 |
| A97309 | 2013 | Troy Resources Ltd.; Western Areas Limited | Sandstone | 2.6% | Sandstone Project, Annual Report for the period 1st January 2012 to 31st December 2012, E57/485......E57/877; |
| A98763 | 2013 | Southern Cross Goldfields Ltd | Sandstone | <1% | Final Surrender Report for the Sandstone Project, E57/576 (C28/2005), for the period 13 February 2006 to 29 Ap |
| A100211 | 2013 | Southern Cross Goldfields Ltd | Sandstone | 18% | Final Surrender Report for the Sandstone Project, E57/642-I, for the period 5 September 2007 to 25 September 2 |
| A96061 | 2012 | Troy Resources Ltd. | Sandstone | <1% | Sandstone Project, E57/877, Annual Report for the period 20 October 2011 to 19 October 2012. |
| A93563 | 2012 | Troy Resources Nl | Sandstone | 2.4% | Sandstone Project Combined Annual Report for the period 1 January 2011 to 31 December 2011, C28/2005 |
| A89872 | 2011 | Troy Resources Nl; Western Areas Nl | Sandstone | 2.4% | Sandstone Project Combined Annual Report: C28/2005_2010A 1 January 2010 to 31 December 2010 |
| A86313 | 2010 | Troy Resources Nl | Sandstone | 2.4% | Sandstone Project, Sandstone, Western Australia, Combined Annual Report for the period 1 january 2009 to 31 De |
| A86765 | 2010 | Troy Resources Nl | Sandstone | <1% | E57/576 Sandstone Partial Surrender Report - For the Period 13 February 2006 to 12 February 2010 |
| A84490 | 2009 | Troy Exploration Nl | Sandstone | 3.3% | E57/584 Sandstone W.A, Partial Surrender Report For the Period 5 October 2005 to 4 October 2009 (C28/2005) |
| A77701 | 2008 | Troy Resources Nl | Sandstone Project | 2.5% | SANDSTONE PROJECT WESTERN AUSTRALIA COMBINED ANNUAL REPORT C28/2005 For the Period 1 January 2007 to 31 Decemb |
| A74809 | 2007 | Troy Resources Nl | Sandstone | 2.9% | Sandstone Project, Sandstone, Western Australia, Combined Annual Report for the Period 1 Jan 2006 to 31 Decemb |
| A72098 | 2006 | Troy Resources Nl | Sandstone/Clackline/Black Hill | 3.2% | Sandstone Project, Sandstone, Western Australia, Combined Annual Report For Period 1 January 2005 to 31 Decemb |
| A73928 | 2006 | Troy Resources Nl | Sandstone | 1% | Sandstone Project Sandstone, Western Australia, Annual Report, for the Period 5 October 2005 to 4 October 2006 |
| A70144 | 2005 | Troy Resources Nl | Maninga Marley | <1% | Maninga Marley Project,Sandstone, Western Australia Annual Report For the Period 1 January 2004 to 31 December |
| A68178 | 2004 | Troy Resources Nl | Sandstone | 27% | Annual Report for the period 26th July 2002 to 25th July 20 03 Sandstone E57/424 Report No SST/04/1/1.1 |
| A68179 | 2004 | Troy Resources Nl | Sandstone | 27% | Partial Surrender Report for the period 26th July 2000 to 25 th July 2003 Sandstone E57/424 Report No SST/04/4 |
| A68296 | 2004 | Troy Resources Nl | Maninga Marley | <1% | Maninga Marley Project, Sandstone, Western Australia, Annual Report for Period 1 January 2003 to 31 December 2 |
| A69551 | 2004 | Troy Resources Nl | Lightning Well / Magnet Road | 17% | Magnet Road Project, E57/208, E57/429, E57/430, Lightning Well Project E57/220, Annual report for the period 2 |
| A69860 | 2004 | Troy Resources Nl | Black Hill | 27% | Annual report for the period 26th July 2003 to 25th July 20 04 E57/424 Sandstone Report No SSV/05/1/1.1 |
| A66339 | 2003 | Troy Resources Nl | Maninga Marley | <1% | Maninga Marley Project, Annual Report for the period 1st January 2002 to 31st December 2002, M57/301. |
| A67237 | 2003 | Troy Resources Nl | Magnet Road - Lighning Well | 17% | Annual Report for the period 29 July 2002 to 28 July 2003, Magnet Road Project, E57/208,429,430 & Lighning W |
| A64401 | 2002 | Troy Resources Nl | Maninga Marley | <1% | Maninga Marley Project, Annual Report for the period 1st January 2001 to 31st December 2001, M57/301. |
| A65080 | 2002 | Croesus Mining Nl | Black Hill | 27% | Black Hill Project Annual Report For The Period 26 April 2001 to 25 April 2002 On The Tenement E57/424. |
| A65186 | 2002 | Troy Resources Nl | Magnet Road - Lighting Well | 17% | Magnet Road Project E57/208, 57/429 & 57/430 & Lighting Well Project E57/220 ,Annual Report for the period 29t |
| A62661 | 2001 | Troy Resources Nl | Maninga Marley | <1% | Maninga Marley Project, Annual Report, P57/690-692 ,for the period 1st January 2000 to 31st December 2000 [C12 |
| A62677 | 2001 | Croesus Mining Nl | Black Hill | 27% | Black Hill Project Annual Report For The Period 26 April 2000 to 25 April 2001 On The Tenement E57/424. |
| A63559 | 2001 | Troy Resources Nl | Magnet Road - Lightning Well | 17% | Combined Annual Report Magnet Road Project E57/208, 57/429 & 57/430 and Lightning Well Project E57/220 Sandsto |
| A61180 | 2000 | Troy Resources Nl | Magnet Road - Lightning Well | 17% | Annual Report, Magnet Road Project, E57/208,429,430 & Lightning Well Project E57/220, for the period 29th Jul |
| A60015 | 2000 | Herald Resources Ltd | Raffertys Patch | <1% | Block Model Mineral Resource Estimates for the Havilah and Maninga Marley Prospects P57/690-692 (Period from 1 |
| A61492 | 2000 | Herald Resources Ltd | Lightning Well | 22% | Lightning Well Project, Partial Surrender Report for the period 16th September 1993 to 17th June 1998, E57/220 |
| A57797 | 1999 | Herald Resources Ltd | Maninga Marley | <1% | Maninga Marley Project Year End 31/12/1998 Prospecting Licence: 57/690-692 |
| A58816 | 1999 | Herald Resources Ltd | Magnet Road - Lightning Well | 17% | Annual Report, Magnet Road/Lightning Well Project, E57/208 and E57/220, 29 July 1998 to 28 July 1999, [C379/19 |
| A53670 | 1998 | Herald Resources Ltd | Maninga Marley | <1% | 1997 Annual Technical Report Maninga Marley Project, P57/690-692 for the period 12/1996 - 12/1997. |
| A53678 | 1998 | Herald Resources Ltd | Sandstone | <1% | Sandstone Project - Annual Report M57/40, 128-130, 179, 192, 248, P57/686-687,, 698-700, etc. Year Ending: 31/ |
| A56100 | 1998 | Herald Resources Ltd | Sandstone - Lightning Well | 22% | Sandstone - Lightning Well Project, Annual Report , E57/220, for the period 16/09/97-15/09/98. |
| A50828 | 1997 | Stockdale Prospecting Ltd | Lake Mason | <1% | Lake Mason Project, First and Final Report E36/300, E36/301;E57/272-276, E57/278-280 & E57/282-289, March 1997 |
| A52752 | 1997 | Herald Resources Ltd | Sandstone- Lightning Well | 22% | 1997 Annual Report for the period 16/09/1966 to 15/09/1997, Sandstone- Lightning Wel lProject, E57/220. |
| A50555 | 1997 | Herald Resources Ltd | Raffertys Patch | <1% | Maninga Marley Project P57/690, P57/691, P57/692 Annual Technical Report for the Year Ending 31 December 1996 |
| A46988 | 1996 | Herald Resources Ltd | Sandstone - Maninga Marley | <1% | Sandstone -Maninga Marley Project, P57/690, P57/691 and P57/692 ,Annual Report for the period 1st January 1 |
| A49128 | 1996 | Herald Resources Ltd | Maninga Marley | 22% | Annual Technical Report E57/220 16 September 1995 to 15 September 1996 (Maninga Marley) |
| A45775 | 1995 | Mt Kersey Mining Nl | Sandstone | 16% | Exploration licences E57/208 & 220 Prospecting Licences P57/769 & 803-5. Sandstone Project, Annual Report for |
| A40465 | 1994 | Gold & Mineral Exploration Nl | Maninga Marley | <1% | Annual report for the period 11/92-12/93 Maninga Marley Project P57/690 P57/691 P57/692 |
| A42887 | 1994 | Mt Kersey Mining Nl | Maninga Marley | 22% | E57/220,Maninga Marley Project, Annual report for the period 16 September 1993 to 15 September 1994. |
| A32233 | 1990 | Carpentaria Exp Co Pty Ltd | Maninga Marley | <1% | Technical report No:1419, Maninga Marley Project Exploration completed between March and November 1990 |
| A28526 | 1989 | Gold & Mineral Exploration Nl | Maninga Marley | <1% | Maninga Marley Project - Gold and Mineral Exploration NL Progress Report to 07/89 (E57/50, E57/148, M57/25 and |
| A21190 | 1987 | Homestake Australia Ltd | Maninga Marley | <1% | Maninga Marley Joint Venture progress report 1 October, 1986 to 31 July, 1987 (HAL Report No. 1987/25) |
| A22683 | 1987 | Litex Contractors Pty Ltd | Maninga Marley | <1% | Maninga Marley Joint Venture Progress report 01/10/86-31/07/87 (Tenements E57/50 M57/25 M57/43) |
| A19597 | 1986 | Homestake Australia Ltd | Maninga Marley | <1% | Maninga Marley Joint Venture Annual report to 30 September, 1986 (HAL Report No. 1986/35) |
| A16621 | 1985 | Homestake Australia Ltd | Maninga Marley | <1% | Maninga Marley Joint Venture Annual report to 30 September, 1985 (HAL Report NO. 1985/26) |
| A14547 | 1984 | Clackline Refractories Ltd | Dandaraga | 13% | Dandaraga Project, Final Surrender Report for theperiod ending 23/11/1984, MC57/5045 & 5046; P57/153. |
| A3591 | 1972 | Kennecott Exp Aust Pty Ltd | Youanmi One | 38% | Youanmi One Project, Non-statutory Report: Stratigraphic Facing at Youanmi One, April 1972, MC57/165-170...... |
| A10529 | 1971 | Kennecott Exp Aust Pty Ltd | Boolygoo | 25% | Boolygoo Project, Non-statutory Report: 1970 Progress Report on Boolygoo Examination, February 1971, MC57/165- |
| A11458 | 1971 | Kennecott Exp Aust Pty Ltd | Boolygoo Examination | 19% | Boolygoo Examination Project, Annual (Progress) Report , 1970, MC57/ 396-399,400-411, 165-170, 173-177, 200-20 |
| A3371 | 1971 | Kennecott Exp Aust Pty Ltd | Youanmi 1 & 2 | 38% | Youanmi 1 & 2 Project, Non-statutory Report:Final Report, Boolygoo Examination for period ending June1971, MC |
| A6936 | 1971 | Kennecott Exp Aust Pty Ltd | Wiluna One (Boolygoo) | 25% | Wiluna One (Boolygoo) Project, Non-statutory Report: Exploration Data: Survey Datum Log, Geophysical Surveys, |
| A2567 | 1970 | Kennecott Exp Aust Pty Ltd | Youanmi One | 38% | Youanmi One Project, Annual Report ( Ground Geopysical Survey) for the period ending 31/12/1970, MC57/165-170 |
| A9685 | 1753 | Western Mining Corporation Ltd | Sandstone | 11% | Sandstone Project, Non-statutory Report: Terminal Report for the period 18th January 1980 to 17th January 1981 |
| A82122 | 1753 | Troy Resources Nl | SANDSTONE | 2.5% | SANDSTONE PROJECT SANDSTONE WESTERN AUSTRALIA COMBINED ANNUAL REPORT For the Period 1 January 2008 to 31 Decem |
| A82964 | 1753 | Troy Resources Nl | Sandstone | 3.3% | E57/584 SANDSTONE WESTERN AUSTRALIA PARTIAL SURRENDER REPORT For the Period 5 October 2005 to 4 October 2008 |
Tenure detail Free account
- Current holders & shares
- Holder change history
- Expenditure history
- Conditions & endorsements
- Native title context
- Combined reporting
- Rent status
Tenement intelligence Premium
- Time to expiry
- 4 years · 18 Jan 2031
- At-risk & opportunity signals
- Expenditure compliance
- 5-year track record
- Spend trend & exploration intensity
- Expiry band
- Ownership age
- Dealings, mortgages & caveats
- Transfer history
What does the exploration record say about this ground?
NextMaps reads every WAMEX report over E 57/1375 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps — every claim cited back to its source report. New accounts include a free prospectivity report. Prefer the raw due diligence? The Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Open on the map — full register record About AI reports About Tenure PacksDo you hold E 57/1375? Listing is free. A facilitation fee applies only if you sell to a buyer we introduce.
List this tenementTenure data sourced from the DMPE public registers and SLIP WA (© Government of Western Australia, CC BY 4.0), as at 2026-08-24. Compiled by NextMaps. Verify against primary sources before reliance.