E 29/1327
Register summary
- Holder
- Wilding Resources Pty Ltd
- Local government
- Shire of Leonora, Shire of Menzies
- Application received
- 25 Feb 2026
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A148309 | 2025 | Javelin Minerals Limited | South Malcolm | <1% | Combined Group Report C5/2024 over Malcolm South Project for the period ending 26/03/2025 |
| A149990 | 2025 | Blue Ribbon Mines Pty Ltd | Cathedrals Belt | <1% | E 29/1030, E 29/1032 and E 29/1035 Partial Surrender Report Cathedrals Belt Project for the period ending 12/0 |
| A149854 | 2025 | Alliance Nickel Limited | Malcolm | <1% | Final Surrender Report E37/1494 Malcolm for the period ending 01/07/2025. |
| A139106 | 2024 | Alliance Nickel Limited | Malcolm | <1% | Annual Report E37/1494 Malcolm for the period ending 19/01/2024. |
| A143589 | 2024 | Javelin Minerals Limited | Mount Ida - Ida Valley | <1% | Peperill Hill Final Report E29/01024 for the period 19/03/2023 to 24/04/2024 |
114 more reports
| A143964 | 2024 | Javelin Minerals Limited | Mount Ida - Ida Valley | <1% | Mt Ida - Ida Valley Final Report E29/01135 for the period ending 24/04/2024 |
| A144936 | 2024 | Javelin Minerals Limited | Mt Ida-Ida Valley | <1% | Mt Ida-Ida Valley Final Report E29/1136 for the period ending 05/07/2024. |
| A145861 | 2024 | Javelin Minerals Limited | South Malcolm | <1% | Combined Group Report C5/2024 over Malcolm South Project for the period ending 21/06/2024 |
| A133859 | 2023 | Xplore Resources Pty Ltd | Knight | <1% | Annual Technical Report for Exploration Activity Knight Project E37/1336, Period Ending 14 November 2022. |
| A136401 | 2023 | Javelin Minerals Limited | Ularring E 29/1134 | <1% | Annual Report E 29/1134 Ularring for the period ending 30/06/2023. |
| A135158 | 2023 | Javelin Minerals Limited | Mount Ida - Ida Valley | <1% | Annual Report E 29/1135 Mt Ida - Ida Valley for the period ending 17/03/2023. |
| A134220 | 2023 | Javelin Minerals Limited | Mt Ida-Ida Valley | <1% | Peperill Hill Annual Report E29/1024 for the period ending 18/03/2023. |
| A135157 | 2023 | Javelin Minerals Limited | Mount Ida-Ida Valley | <1% | E 29/1137 Annual Report Mt Ida-Ida Valley for the period ending 17/03/2023. |
| A135436 | 2023 | Javelin Minerals Limited | Mt Ida-Ida Valley | <1% | Annual Report E 29/1136 Mt Ida-Ida Valley for the period ending 11/04/2023. |
| A131137 | 2022 | Xplore Resources Pty Ltd | Dragon | 100% | Annual Tenure Report for Exploration Activity Dragon Project E29/1034, Period Ending 02 May 2022. |
| A130718 | 2022 | Javelin Minerals Limited | Mount Ida-Ida Valley | <1% | Mt Ida-Ida Valley E29/01024 Peperill Hill Annual Report for the period ending 18/03/2022 |
| A125789 | 2021 | Xplore Resources Pty Ltd | Knight | <1% | Annual Technical Report for Exploration Activity Knight Project E37/1336, Period Ending 14 November 2020 |
| A127068 | 2021 | Victory Mines Ltd | Peperill Hill | <1% | Annual Technical Report for Peperill Hill E29/01024 for the period 19 March 2020 to 18 March 2021 |
| A127435 | 2021 | Xplore Resources Pty Ltd | Dragon | 100% | Annual Tenure Report for Exploration Activity Dragon Project E29/1034, Period Ending 02 May 2021 |
| A129151 | 2021 | Xplore Resources Pty Ltd | Knight | <1% | Annual Technical Report For Exploration Activity Knight Project E37/1336, Period Ending 14 November 2021 |
| A124021 | 2020 | Tyranna Resources Limited | Dragon | 100% | Dragon Project E 29/01034 Annual Report for the period ending 2 May 2020 |
| A123886 | 2020 | Victory Mines Ltd | Peperill Hill | <1% | Annual Technical Report for Peperill Hill E29/01024 for the period ending 18/03/2020 |
| A122629 | 2020 | Xplore Resources Pty Ltd | Knight | <1% | Knight project (tenure E37/1336) Annual Technical Report For Exploration Activity for the period 15 November 2 |
| A123771 | 2020 | Aldoro Resources Limited | Cathedrals | <1% | Cathedrals Belt Project E29/1030 Annual Report for the period ending 14/03/2020 |
| A120133 | 2019 | Victory Mines Pty Ltd | Peperill Hill | <1% | Annual Report for Peperill Hill E29/1024 for the period 19 March 2018 to 18 March 2019 |
| A119925 | 2019 | Talisman Nickel Pty Ltd | Sinclair | <1% | Sinclair Nickel Project Combined Annual Report C1/2006 for the period 17 February 2018 to 16 February 2019 |
| A120642 | 2019 | Talisman Nickel Pty Ltd | Bannockburn | <1% | Final Surrender Report for Tenement E37/903 Bannockburn project for the period 22 September 2008 to 3 April 2 |
| A116758 | 2018 | Talisman Nickel Pty Ltd | Sinclair | <1% | Sinclair Nickel Project Combined Annual Exploration Report C1/2006 for the period 17 February 2017 to 16 Febru |
| A113848 | 2017 | Talisman Nickel Pty Ltd | Sinclair | <1% | Sinclair Nickel Project C1/2006 Annual Report for the period 17 February 2016 to 16 February 2017, E36/00650.. |
| A108700 | 2016 | Lake View | 6.5% | Kalgoorlie Core Library Drill Hole Report Hole ID ELV071, From Lake View Project E29/577 | |
| A108580 | 2016 | Talisman Nickel Pty Ltd | Sinclair | <1% | Combined Annual Exploration Report Sinclair Nickel Project C1/2006 for the period 17 February 2015 to 16 Febru |
| A104990 | 2015 | Energy Metals Ltd | Mopoke Well | 31% | Partial Surrender Report E29/568 Mopoke Well for the period 5 January 2006 – 23 December 2014 |
| A105505 | 2015 | Talisman Mining Ltd | Sinclair | <1% | Sinclair Nickel Project Combined Annual Exploration Report C1/2006 For the Period 17 February 2014 to 16 Febru |
| A106185 | 2015 | Energy Metals Ltd | Mopoke Well | 31% | Mopoke Well Project E29/568 Final Technical Report for the period 05/01/2006 - 14/05/2015 |
| A106258 | 2015 | Energy Metals Ltd | Mopoke Well | 31% | Combined Annual Report E29/568 & E29/623, C136/2011 Mopoke Well Project for the period 1 April 2014 – 31 March |
| A102363 | 2014 | Xstrata Nickel Australasia Operations Pty Ltd | Bannockburn | <1% | Bannockburn Project, Annual Report for the period 17/02/2013 to 16/02/2014, E36/581 & 650; E37/538, 852-853, 9 |
| A102305 | 2014 | Energy Metals Ltd | Mopoke Well | <1% | Mopoke Well Project, E29/623, Final Surrender Report for the period 16 March 2010 to 21 March 2014, |
| A102750 | 2014 | Energy Metals Ltd | Mopoke Well | 26% | Mopoke Well Project, C136/2011 COMBINED ANNUAL REPORT FOR THE PERIOD ENDING 31st MARCH 2014 (COVERING E29/568 |
| A97028 | 2013 | Hlm Australia Pty Ltd | Pepperill Hill | <1% | Pepperill Hill Project, Final Surrender Report , E29/832. [for the period 14th December 2011 to 13th December |
| A96821 | 2013 | Areva Resources Australia | Lake Raeside 2 | <1% | Final Surrender Report For the period 21 July 2011 to 20 November 2012 Lake Raeside 2 Project E37/1089 |
| A97333 | 2013 | T E Johnston & Assciates Pty Ltd | Bannockburn | 11% | Bannockburn Project, Annual Report for the period 02/02/2012 to 01/02/2013, E37/943 & 1006. [C153/2010] |
| A98340 | 2013 | Energy Metals Ltd | Mopoke Well | 26% | Mopoke Well Project C136/2011 combined annual report for the period ending 31st March 2013 (covering E29/568 & |
| A96820 | 2013 | Areva Resources Australia | Sturt Meadows | <1% | Final Surrender Report For the period 14 April 2010 to 20 November 2012 Sturt Meadows Project E37/1020 |
| A98097 | 2013 | Xstrata Nickel Australasia Operations Pty Ltd | Bannockburn | <1% | Bannockburn Project, Annual Report for the period 17th February 2012 to 16th February 2013, E36/581 & 650; E37 |
| A99194 | 2013 | Spark Energy Pty Ltd | Raeside | 27% | Raeside Project E37/1101 Final report for the period 22 June 2012 to 9 July 2013 |
| A100798 | 2013 | Xstrata Nickel Australasia Operations Pty Ltd | Bannockburn | <1% | Bannockburn Project, Final Surrender Report for the period 28/10/2008 to18/12/2013, P36/1714-1719; E36/581; M3 |
| A93011 | 2012 | Te Johnston And Associates Pty Ltd | Bannockburn | 11% | Annual Technical Report Group C153/2010, E37/943 and E37/1006 for the period 2/2/2011 to 1/2/2012, Bannockbu |
| A93500 | 2012 | Afmeco Mining & Exploration Pty Ltd | North Yilgarn | <1% | Annual Report For the period 14 April 2011 to 14 April 2012, North Yilgarn Project E37/1020 |
| A93862 | 2012 | Xstrata Nickel Australasia Operations Pty Ltd | Bannockburn | <1% | Bannockburn Project C1/2006 Annual Report for the Period 17th February 2011 to 16th February 2012 |
| A94000 | 2012 | Energy Metals Ltd | Mopoke | 26% | Mopoke Well Project C136/2011 Combined Annual Report for the period ending 31st March 2012 (covering E29/568 & |
| A95638 | 2012 | Areva Resources Australia | North Yilgarn | <1% | Annual Report For the period 1 August 2011 to 31 July 2012 North Yilgarn Project E37/1019, 1020, 1089 (C34/201 |
| A96518 | 2012 | Areva Resources Australia | North Yilgarn | <1% | Annual Report For the period 1 August 2011 to 31 July 2012 North Yilgarn Project E37/1019, 1020, 1089 |
| A90085 | 2011 | Energy Metals Ltd | Mopoke Well | 31% | Mopoke Well Project, Annual Report for the period ending 4th January 2011, E29/568. |
| A90340 | 2011 | Xstrata Nickel Australasia Operations Pty Ltd | Bannockburn | <1% | Bannockburn Project, Annual Report for the period 17th February 2010 to 16th February 2011, Tenements as per C |
| A88985 | 2011 | Encounter Resources Ltd | Lakeview | 6.5% | Lakeview Project, Annual Report for the period 16th December 2009 to 13th December 2010, E29/577. |
| A86122 | 2010 | Energy Metals Ltd | Mopoke Well | 31% | Mopoke Well, Project E29/568 Annual Report for the period ending 4th January 2010 |
| A89754 | 2010 | Te Johnston And Associates Pty Ltd | Bannockburn | 11% | Annual Technical Report Group C153/2010 E37/943 and E37/1006 for the period 2/2/2010 to 1/2/2011 Bannockburn P |
| A85482 | 2010 | Encounter Resources Ltd | Lakeview | 6.5% | Lakeview Project E29/577, Annual Report for the Period 16 December 2008 to 15 December 2009, |
| A86949 | 2010 | Xstrata Nickel Australasia Opertions Pty Ltd | Bannockburn | <1% | Bannockburn Project C1/2006 Annual Report for the Period 17th February 2009 to 16th February 2010, M37/383, M3 |
| A88636 | 2010 | Red Oak Pry Ltd | Red Oak | <1% | Annual Mineral Exploration Report RED OAK PROJECT E29/617 For the Period 14 August 2009 to 13 August 2010 |
| A81043 | 2009 | Energy Metals Ltd | MOPOKE WELL | 31% | MOPOKE WELL PROJECT E 29/568, ANNUAL REPORT FOR THE PERIOD ENDING 4th JANUARY 2009 |
| A81716 | 2009 | Encounter Resources Ltd | Lakeview | 6.5% | Lakeview Project E29/577, Annual Report for the period 16 December 2007 to 15 December 2008 |
| A82397 | 2009 | Encounter Resources Ltd | Lakeview | 6.5% | Lakeview Project, E29/577, Partial Surrender Report for the period 16 December 2005 to 15 December 2008. (Leon |
| A84135 | 2009 | Xstrata Nickel Australasia Opertions Pty Ltd | Bannockburn | <1% | Annual Exploration Report on The Bannockburn Project Tenements For the Period 17th February 2008 to 16th Febru |
| A78172 | 2008 | Energy Metals Ltd | Mopoke Well | 31% | Mopoke Well Project E29/568 Annual Report for the period ending 4th January 2008 North Coolgardie Mineral Fiel |
| A79837 | 2008 | Eagle Eye Metals Ltd | Sturt Meadows | <1% | E37/783, Annual report 2008 for Sturt Meadows Project, Report Period: 18 April 2007 – 17 April 2008 |
| A77379 | 2008 | Encounter Resources Ltd | Lake View | 6.5% | Lakeveiw Project E29/577 Annual report for the period 16 December 2006 to 15 December 2007. (Leonora) |
| A77466 | 2008 | Energy Metals Ltd | Mopoke Well | 31% | MOPOKE WELL PROJECT E29/568 ANNUAL REPORT FOR THE PERIOD ENDING 4th JANUARY 2007 |
| A78217 | 2008 | Jubilee Mines Nl | Bannockburn | 1.8% | Annual Exploration Report on The Bannockburn Project Tenements For the Period 17th February 2007 to 16th Febru |
| A79836 | 2008 | Mr Johnson Ng | Sturt Meadows | <1% | E37/783, Annual report 2007 for Sturt Meadows Project, Report Period: 18 April 2006 – 17 April 2007 |
| A74354 | 2007 | Energy Metals Ltd | Mopoke Well | 31% | Mopoke Well Project E29/568 Annual Report for the Period Ending 4th January 2007 (Leonora) |
| A74968 | 2007 | Jubilee Mines Nl | Bannockburn | 2% | Annual Exploration Report on The Bannockburn Project over E36/183, E37/224, 253, etc. For the Period 17th Feb |
| A74586 | 2007 | Encounter Resources Ltd | Lake View | 6.5% | Lake View Project E29/577 Annual Report for the Period 16th Dec 2005 to 15th Dec 2006, (Leonora) |
| A72376 | 2006 | Jubilee Mines Nl | Bannockburn | 2% | Annual Exploration Report on the Bannockburn Project over E36/183, E37/224, E37/253, etc., For the Period 1 Ja |
| A72673 | 2006 | Bhp Billiton Minerals Pty Ltd | Ida Valley | 4.7% | Ida Valley Project, Partial Surrender Report for the period 24th October 2001 to 3rd July 2006, E29/483. |
| A73395 | 2006 | Bhp Billiton Iron Ore Pty Ltd | Ida Valley | 2.4% | Combined Annual Report C126/2002, For the Period 1 July 2005 to 30 June 2006, Ida Valley Project E29/483, E29/ |
| A73917 | 2006 | Bhp Billiton Nickel West Pty Ltd | Ida Valley | 4.7% | Relinquishment Report for the Period 15 January 2002 to 23 November 2006, Ida Valley Project E29/483, (Leonora |
| A70218 | 2005 | Breakaway Resources Ltd | Bannockburn | 1.7% | Annual technical report, Bannockburn project, E36/183, E37/224, 253, 287, E37/295, 431, 432, 457, 502, M37/135 |
| A70987 | 2005 | Wmc Resources Ltd | Ida Valley | 2.4% | Combined annual report: C126/2002, For the period 1 July 2004 to 30 June 2005, Due:31st August 2005. Ida Valle |
| A68280 | 2004 | Jubilee Mines Nl | Bannockburn | 1.6% | Bannockburn Project, Annual Technical Report E36/183, E37/224, E37/253, E37/287, E37/295, E37/431, E37/432, E |
| A69174 | 2004 | Wmc Resources Ltd | Ida Valley | 2.4% | Ida Valley Project, Annual Report E29/483 & E29/484 for the period 01/07/2003-30/06/2004 (C126/2002). |
| A67227 | 2003 | Wmc Resources Ltd | Ida Valley | 2.4% | Annual Report for the period 1 July 2002 - 30 June 2003 Nickel Exploration, E29/483,E29/484, C126/2002: ( Ida |
| A66287 | 2003 | Jubilee Mines Nl | Bannockburn | 1.6% | Annual Exploration Report for the period 1st January 2002 to 31st December 2002 The Bannockburn Nickel/Base Me |
| A64203 | 2002 | Breakaway Resources Ltd | Bannockburn | 1.7% | Annual Technical Report Bannockburn Project E36/183, E37/224 E37/253, E37/287, E37/295, E37/431, E37/432, E37/ |
| A61959 | 2001 | Arrow Resources Management Pty Ltd | Bannockburn | 1.1% | Annual Technical Report Bannockburn Project E36/183, E36/334 E37/201, E37/202, E37/224, E37/253, E37/287, E37/ |
| A63250 | 2001 | Anaconda Nickel Ltd | Lookout Well | 2.8% | Technical Report TR 1187 Lookout Well project. Surrender Report E37/638 for the Period 11 December 2000 to 2 M |
| A62392 | 2001 | Arrow Resources Management Pty Ltd | Bannockburn | 3.7% | Surrender And Partial Relingquishment Report Bannockburn Project E37/401, E37/430, E37/431, E37/432 & E37/497 |
| A57918 | 1999 | Astro Mining Nl | West Leonora | <1% | Exploration Licences E29/225, 271, 272 (all tenements worked on ) Joint Annual Report for the Period 6th Decem |
| A57501 | 1999 | Western Diamond Corporation Nl | Raeside | 12% | Annual mineral exploration report for E29/284-287,301,319,321,454,463. 01/01/98-31/12/98. (Raeside Project). |
| A57875 | 1999 | Consolidated Gold Mines Ltd | Bannockburn | 1.3% | Bannockburn Project 01/01/98 - 31/12/98 E36/183, E37/201, 224, 253 |
| A54516 | 1998 | Stockdale Prospecting Ltd | Leonora | 54% | Leonora Project, Annual Report , E37/266, 04/1998 |
| A54474 | 1998 | Stockdale Prospecting Ltd | Leonora | 54% | Leonora Project, Partial Surrender Report ,E37/266, for the period 28/10/1992 to 22/10/1997. |
| A54613 | 1998 | Consolidated Gold Mines Ltd | Bannockburn | 1.3% | Bannockburn Project, Regional Exploration Annual Report 1997, E36/183, E37/201, 224, 253 |
| A54620 | 1998 | Consolidated Gold Mines Ltd | Banncockburn - Lake Raeside | 5.4% | Banncockburn- Lake Raeside Project, , Annual Report: 1997 E37/432. |
| A54621 | 1998 | Consolidated Gold Mines Ltd | Bannockburn - Sturt Meadows | 1.2% | Bannockburn- Sturt Meadows Project,, Annual Report 1997 Exploration Licence: E37/431 |
| A55258 | 1998 | Stockdale Prospecting Ltd | Leonora | 54% | Leonora Project, Final Surrender Report for the period 28/10/1992 to 07/05/1998, E37/266. |
| A53736 | 1998 | Astro Mining Nl | West Leonora | 1% | Exploration Licences : E29/211-226,271-272 ;E36/262-269 Joint Annual Report for the Period 06 December1996 to |
| A50122 | 1997 | Astro Mining Nl | West Leonora | 1% | West Leonora Project, Annual Report for the period 6th December 1995 to 5th December 1996, |
| A57037 | 1997 | Consolidated Gold Mines Ltd | Miranda | 1.1% | Miranda Project-M36/34, 61-64, 69-75, 77, 89 etc. Bannockburn Project-M37/135, 339, E37/201, 224, 253,287 etc. |
| A52477 | 1997 | Western Diamond Corporation Nl | Raeside | 21% | Annual Mineral Exploration Report for Exploration Licences E29/281, E29/284, E29/286 & E29/287 Period From 2 |
| A53141 | 1997 | Western Diamond Corporation Nl | Sturt Meadows / Raeside / Perrinvale / M | 12% | Annual Mineral Exploration Report, Exploration Licence: E29/281, 284-287, 301, 319, 321 etc. 25/03/96 - 31/12/ |
| A57038 | 1997 | Australian Gold Fields Nl | Miranda | 1.1% | Miranda Project, Cottees Project, Bannockburn Project, Mt Ida Project. E26/133, 183, 252, 258 01/11/96 |
| A47830 | 1996 | Stockdale Prospecting Ltd | Leonora | 54% | Annual report on E37/266 Leonora Project, Western Australia April 1995 to April 1996 |
| A49805 | 1996 | Stockdale Prospecting Ltd | Leonora | 54% | Partial Surrender Report on E37/266 Leonora Project December 1996 |
| A46762 | 1996 | Astro Mining Nl | West Leonora | 1.1% | West Leonora Project, Reporting Period 6/12/1994 - 5/12/1995, Exploration Licences E29/211-233, E29/2226 and E |
| A44968 | 1995 | Stockdale Prospecting Ltd | Leonora | 16% | Final report, Exploration licences 29/123-126, Leonora area, WA, |
| A46760 | 1995 | Stockdale Prospecting Ltd | Leonora | 54% | Partial Surrender Report for the period 28/10/1992 to 03/01/1996 Leonora Project E37/266 |
| A41230 | 1994 | Stockdale Prospecting Ltd | Leonora | 17% | Annual Report for the period 07/02/93 to 06/02/94 Leonora Project E29/123 to E29/126, E37/220, E37/221 and E37 |
| A41367 | 1994 | Stockdale Prospecting Ltd | Leonora | 12% | Leonora Project, Partial Surrender Report, March 1994, E29/123-126, & E37/220-221. |
| A38357 | 1993 | Stockdale Prospecting Ltd | Leonora | 12% | Annual report for the period 07/02/92-06/02/93 Leonora Project E29/123-126 E37/220 E37/221 |
| A35267 | 1992 | Stockdale Prospecting Ltd | Leonora | 12% | Annual report for the period 07/02/91-06/02/92, Leonora Project, E29/123-126 E37/220 E37/221 |
| A8239 | 1979 | Esso Australia Ltd | Lake Raeside | 15% | Lake Raeside Project, Annual Report for the year ending 31/12/1978, MC29/3001-3008 & MC29/3071-3085. |
| A7512 | 1978 | Esso Australia Ltd | Lake Raeside | 15% | Lake Raeside Project, Annual Report for the peruiod ending 31/12/1977, MC29/3001-3008 & 3071-3085. |
| A7675 | 1978 | Bp Minerals Aust Pty Ltd | Lake Raeside | 60% | Lake Raeside Project, Annual Report for the year ending 31/12/1977, MC29/2945-2957 & 3024-3027. |
| A6749 | 1976 | Bp Minerals Aust Pty Ltd | Lake Raeside | 20% | Lake Raeside Project, Annual Report for the year ending 31/121976, MC29/2949-2966, 3024-3027 & MC37/4980-4991. |
| A6635 | 1975 | Bp Minerals Aust Pty Ltd | Lake Raeside | 20% | Lake Raeside Project, Annual Report , November 1975 (Drilling Programme & Results), MC29/2945-2966; MC37/4980- |
| A6846 | 1753 | Esso Australia Ltd | Lake Raeside | <1% | Lake Raeside Project, Annual Report for the period 01/01/1976 to 31/12/1976, MC29/3001-3017. |
| A51038 | 1753 | Stockdale Prospecting Ltd | Leonora | 54% | Annual report on E37/266 Leonora Project, Western Australia April 1996 to April 1997. |
| A38751 | 1753 | Inco Australia Ltd | Eastern Goldfields regional mapping | <1% | Eastern Goldfields regional mapping |
Tenure detail Free account
- Current holders & shares
- Holder change history
- Expenditure history
- No expenditure obligation until granted
- Conditions & endorsements
- Native title context
- Combined reporting
- Rent status
Tenement intelligence
Expenditure compliance, expiry and ownership-age signals become available once this application is granted. E 29/1327 is a pending application, so it has no expenditure obligation, expiry date or ownership history yet.
What does the exploration record say about this ground?
NextMaps reads every WAMEX report over E 29/1327 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps — every claim cited back to its source report. New accounts include a free prospectivity report. Prefer the raw due diligence? The Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Open on the map — full register record About AI reports About Tenure PacksDo you hold E 29/1327? Listing is free. A facilitation fee applies only if you sell to a buyer we introduce.
List this tenementTenure data sourced from the DMPE public registers and SLIP WA (© Government of Western Australia, CC BY 4.0), as at 2026-08-24. Compiled by NextMaps. Verify against primary sources before reliance.