E 08/2996
Register summary
- Holder
- Techgen Metals Ltd
- Local government
- Shire of Ashburton, Shire of Upper Gascoyne, Shire of Meekatharra
- Application received
- 17 May 2018
- Commenced
- 9 Oct 2019
- Expiry
- 8 Oct 2029
- Term
- 5 Years (Extended)
Exploration history on this ground
| Report | Year | Operator | Project | On this ground | Title |
|---|---|---|---|---|---|
| A150326 | 2025 | Techgen Metals Ltd | Mt Boggola | 60% | Partial Surrender Report E 08/2996 Mt Boggola for the period ending 08/10/2025. |
| A140642 | 2024 | Diversified Asset Holdings Pty Ltd | Sheppards Bore | <1% | Sheppards Bore E 08/3016 Annual Exploration Report for the period ending 14/01/2024. |
| A133989 | 2023 | Techgen Metals Ltd | Mt Boggola | 60% | Mt Boggola_EIS_Final Geological Report (Round 24)_2023 |
| A136921 | 2023 | Diversified Asset Holdings Pty Ltd | Sheppards Bore | <1% | Sheppards Bore E 08/3016 Annual Exploration Report for the period ending 14/01/2023 |
| A130955 | 2022 | Diversified Asset Holdings Pty Ltd | Sheppard's Bore | <1% | Sheppard's Report E 08/3016 Annual Exploration Report for the peiod ending 14/01/2022. |
44 more reports
| A127927 | 2021 | Diversified Asset Holdings Pty Ltd | Sheppard Bore | <1% | Sheppard Bore E08/03016 Annual Report for the period ending 14/01/2021 |
| A125424 | 2020 | Tasex Geological Services Pty Ltd | Mount Boggola | 60% | Mt Boggola E08/2996 Annual Report for the period ending 08/10/2020 |
| A117115 | 2018 | Northern Star Resources Ltd | Ashburton Regional | 1.2% | Final Technical Report for E08/2475 Ashburton Regional Project for the period 12 November 2014 to 16 May 2018 |
| A117126 | 2018 | Northern Star Resources Ltd | Ashburton Regional | 30% | Final Technical Report for E08/2716 Ashburton Regional Project for the period 18 December 2015 to 16 May 2018 |
| A111980 | 2017 | Cosmopolitan Minerals Ltd | Fords | <1% | C36/2016 Fords Creek Project For the Period 9 October 2015 to 8 October 2016 E08/02639, E08/02685, E08/02811, |
| A114480 | 2017 | Northern Star Resources Ltd | Ashburton | 5.3% | C175/2014 Ashburton Regional Annual Technical Report For the Period 1 July 2016 to 30 June 2017, E08/02475, E0 |
| A109733 | 2016 | Northern Star Resources Ltd | Ashburton Regional | 2.7% | Annual Mineral Exploration Report for the Ashburton Regional Group C109/2012 for the period 01/07/2015 to 30/0 |
| A106353 | 2015 | Baracus Pty Ltd | Charlie Creek | 30% | Final Surrender Report for Charlie Creek Project E08/2515 for the period 12/03/2014 to 02/04/2015 |
| A96808 | 2013 | Rising Mining Holdings Pty Ltd | Charlie Creek | 31% | 2013 FINAL SURRENDER REPORT EXPLORATION LICENCE 08/1951 (Charlie Creek Project, for the period 05/03/2012 to 0 |
| A93577 | 2012 | Rising Mining Holdings Pty Ltd | Charlie Creek | 31% | Annual Report on Charlie Creek Project Exploration Licence 08/1951, Reporting Period: 05/03/2011 – 05/03/2012 |
| A89218 | 2011 | Golden Zen Pty Ltd | Ashburton Downs | 4.3% | ANNUAL EXPLORATION REPORT FOR ASHBURTON DOWNS PROJECT TENEMENT EL08/1886 FOR THE PERIOD ENDING 8TH SEPTEMBER 2 |
| A90418 | 2011 | United Mining Resources Pty Ltd | Charlie Creek | 31% | Charlie Creek Project, Annual Report for the period 11/02/2010 to 11/02/2011, E08/1951. |
| A78053 | 2008 | Aurora Minerals Ltd | Capricorn | <1% | ANNUAL TECHNICAL REPORT CAPRICORN PROJECT BANGEMALL BASIN WA TENEMENT GROUP CODE C7/2008, Year ending 31 Decem |
| A71068 | 2005 | Sunrise Exploration Pty Ltd | Pingandy Creek | 7.1% | Pingandy Creek Project (E08/1321) Final report to Department of Industry and Resources for the period 18/08/20 |
| A69257 | 2004 | Sunrise Exploration Pty Ltd | Pingandy Creek | 7.1% | Annual report for the period 18/08/2003-17/08/2004 Pingandy Creek Project E08/1321 |
| A63351 | 2001 | Goldfields Exploration Pty Ltd | Mount Boggola | 9.8% | Surrender Report Mt Boggola E08/1129. |
| A54271 | 1998 | Mr Boyer Dd | Mount Boggola | 7.3% | Mt Boggola Gold Project, Surrender Report-E08/815, Final Surrender Report for Reporting Period 01/12/1995 to 1 |
| A57923 | 1998 | Xplore Pty Ltd | Charlie Creek/ Mount Vernon/ Tchintaby/ | 5.1% | Riverglen Joint Venture , E08/662 Charlie Creek, E08/740 Mt Vernon, E52/785 Tchintaby, E52/956 Regan Yard Surr |
| A50581 | 1997 | Mim Exploration Pty Ltd | Charlie Creek /Mount Vernon/ Tchintaby/ | 5.1% | Annual Report on Exploration carried out during 1996 on E08/662 (Charlie Creek), E08/740 (Mt Vernon), E52/785 |
| A50004 | 1997 | Resource Management Group Pty Ltd | Mount Boggola | 7.3% | Mt Boggola Gold Project Technical Report- E08/815 from 1/12/1995 to 30/11/1996 |
| A50005 | 1997 | Resource Management Group Pty Ltd | Mount Boggola | 7.3% | Mt Boggola Gold Project Surrender Report E08/815 Partial Surrender Report 1/12/1995 to 29/11/1996 |
| A52620 | 1997 | Mim Exploration Pty Ltd | Charlie Creek - Pigott Peak | 27% | Charlie Creek - Pigott Peak Project, Non-statutory Report: RC Drilling Programme, Pigott Peak Prospect, June 1 |
| A48360 | 1996 | Mim Exploration Pty Ltd | Charlie Creek / Mount Vernon, / Tchintab | 5.1% | Charlie Creek / Mt Vernon, / Tchintaby / Regan Yard Project, 1995 Annual Report, July 1996, E08/662 (Charlie C |
| A43784 | 1995 | Riverglen Pty Ltd | Charlie Creek | 27% | Charlie Creek Project, Annual Report Exploration Licence E08/662 for year ending 4th October 1994. |
| A44840 | 1995 | Pasminco Exploration | Peebeezee | 10% | Peebeezee JV Project. Partial surrender report for E08/447. |
| A43942 | 1995 | Pasminco Exploration | Peezeebee | 3.3% | Peezeebee Project, Annual Report E08/447, 456, 603 & 634 for the period ending 31st December 1994. |
| A46646 | 1995 | Pasminco Exploration | Peebeezee | 3.5% | Peebeezee (JV) Project, Final Surrender Report for the period 02/05/1991 to 30/10/1995, E08/447, E08/603 & E0 |
| A40230 | 1994 | Pasminco Exploration | Peebeezee | 3.3% | Peebeezee Project, Annual Report, February 1994, E08/447, 456, 603 & 634. |
| A39214 | 1993 | Newcrest Mining Ltd | Pingandy - Boggola | 5.9% | Pingandy - Boggola Project , Final Surrender Report for E52/504 & 505, E08/333 & 455; Partial Surrender Report |
| A37793 | 1993 | Newcrest Mining Ltd | Pingandy -Boggola | 5.1% | Pingandy -Boggola Project, Annual Report for the period 01/01/1992 to 31/12/1992, E08/333, 447,455-456, & 504- |
| A35154 | 1992 | Newcrest Mining Ltd | Pingandy Boggola | 3.1% | Pingandy Boggola Project, Annual report for 1992, E08/333E08/445-447, E08/455/456, E08/465, E08/504-505, E08/5 |
| A36872 | 1992 | Newcrest Mining Ltd | Piggandy Boggola | 3.1% | Piggandy Boggola Project, Partial Surrender Report, E08/465, E08/445, E08/446, E08/447, E08/455, E08/456, E08/ |
| A34496 | 1991 | Newcrest Mining Ltd | Mount Boggola | 8.9% | Mount Boggola, Annual report for the period 7 June 1990 to 6 June 1991, E08/333 |
| A30935 | 1990 | Australmin Holdings Ltd | Mount Boggola | 8.9% | Mt Boggola Project, Annual Report for the period 7th June 1989 to 6th June 1990, E08/333. |
| A26646 | 1989 | Billiton Australia Pty Ltd | Mount Boggola - Charlie Creek | 9.3% | 1st Annual [and final] Report for E08/247 and 08/252, Mt Boggola and Charlie Creek , April 1989. |
| A28666 | 1989 | Metana Minerals Nl | Ashburton | <1% | The Ashburton Project Final report, March 1989 E8/130, E08/135 to E08/145, E08/245, E08/246, M08/5, M08/25, M |
| A21559 | 1987 | Alcoa Of Australia Ltd | Bangemall Basin | <1% | Bangemall Basin, [Non-statutory Report: Mapping, circa 1966] |
| A13448 | 1983 | Noranda Australia Ltd | McLeods Bore | 53% | McLeods Bore Project, Annual Report for the period ending 31/12/1982, MC08/3574-3577 & 3629-3635. |
| A11537 | 1982 | Cra Exploration Pty Ltd | Mount Boggola | 6% | Final Report on Exploration Completed within Temporary Reserves 8412H Mt. Boggila, 8413H Little Pingandy and 8 |
| A9696 | 1981 | Otter Exploration Nl | Mount Boggola | 19% | Mount Boggola Project, Non-statutory Report: Final Report, January 1981, TR7495H. |
| A21557 | 1972 | Alcoa Of Australia Ltd | Bangemall Basin | <1% | Bangemall Basin Project, Non-statutory Report: Edmund Area, Plates 1- 5, January 1972, |
| A1595 | 1966 | Ashburton Exp Pty Ltd | M62/0: Ashburton-Bangemall base metal/as | <1% | TR2924H Ashburton Exploration Summary Report for 1965. Programme 1966. |
| A566 | 1964 | Westfield Minerals Nl | Ashburton-Bangemall | <1% | Ashburton-Bangemall Project, Non-statutory Report: Summary Report for 1963 & Projected Development Programme 1 |
| A81037 | 1753 | Aurora Minerals Ltd | CAPRICORN | 2.1% | Surrender Report for Capricorn Projec tPart of Common Reporting Number C7/2008 |
Tenure detail Free account
- Current holders & shares
- Holder change history
- Expenditure history
- Conditions & endorsements
- Native title context
- Combined reporting
- Rent status
Tenement intelligence Premium
- Time to expiry
- 3 years · 8 Oct 2029
- At-risk & opportunity signals
- Expenditure compliance
- 5-year track record
- Spend trend & exploration intensity
- Expiry band
- Ownership age
- Dealings, mortgages & caveats
- Transfer history
What does the exploration record say about this ground?
NextMaps reads every WAMEX report over E 08/2996 into a referenced prospectivity assessment: the geology, the historical programs, the drill intercepts and geochemistry, and the untested gaps — every claim cited back to its source report. New accounts include a free prospectivity report. Prefer the raw due diligence? The Tenure Pack bundles the full register record, tenure history and spatial datasets for this ground.
Open on the map — full register record About AI reports About Tenure PacksDo you hold E 08/2996? Listing is free. A facilitation fee applies only if you sell to a buyer we introduce.
List this tenementTenure data sourced from the DMPE public registers and SLIP WA (© Government of Western Australia, CC BY 4.0), as at 2026-08-24. Compiled by NextMaps. Verify against primary sources before reliance.